MS Project Server 2003 Tips
Is it right to call it tip or finding, I don't know. Feel free to comment on it.
Project Server Resource Center avalibility grid and diagram don't update real time if users send new or changed assignments to the PServer. I found out that it there is appr. 1 hr delay to update. I haven't looked into the reasons in detail, however here is what i found to overcome the issue. To make the update real time, have the plans Published with "Send All Information". This feature updates the views real time. Anybody knows the reason?
Project Server Resource Center avalibility grid and diagram don't update real time if users send new or changed assignments to the PServer. I found out that it there is appr. 1 hr delay to update. I haven't looked into the reasons in detail, however here is what i found to overcome the issue. To make the update real time, have the plans Published with "Send All Information". This feature updates the views real time. Anybody knows the reason?